Bosch-Siemens at Prologis Park Kettering banner

Bosch-Siemens at Prologis Park Kettering

The Requirement

  • BSH Home Appliances, the distribution arm of BSH Bosch und Siemens Hausgeräte, needed a new 400,000 sq ft UK distribution facility quickly. It was vital that the company was able to move into its new premises by early December to prepare for the post-Christmas sales rush

The Solution

  • Prologis was able to work to provide a site of the right size with planning permission at its site in Kettering
  • The team worked with BSH to modify the existing design to create a building of 427,000 sq ft including 20,000 sq ft of offices over two floors and 10,000 sq ft of support/hub offices
  • Following a 30 week programme the building was completed and fitted out on 5 December

The Result

"Prologis was flexible in all its dealings. They allowed us early access to our warehouse and fitted out our heating, lighting and sprinkler systems so that we could move in to meet our own deadline."

Colin Blake, Chief Finance Officer, BSH Home Appliances Ltd

Photo gallery

green-arrow-small-leftClick to view case studies listing